Guide To Your Koto House

Using Koto Designs & Plans
  • Kindly make a selection of your dream house type at KOTO HOUSE DESIGNS
  • Complete the online application form at KOTO House Application Form
  • Pay relevant commitment fees (Kshs. 100,000 for bungalows and maisonettes, Kshs. 300,000 for projects with multiple units and Kshs. 50K for a classroom.
  • Payment of Commitment fees facilitates the following items
  • Preparation of Architectural plans | Structural Plans | Bill of quantities for the chosen house type and enables us to visit your site.

  • Upon receipt of the items above, Submit your plans to your county for approval.
  • Organise financing for the construction cost e.g Savings, Take a Mortgage Loan from one of our partners.
  • Submit approved building plans to KOTO housing Kenya
  • Sign the KOTO Construction Delivery Contract
  • Pay the construction cost as per the agreed Priced Bills of Quantities.
  • KOTO Housing Kenya Limited builds your house as per the construction contract.
Using Your Own Approved Building Plans
  • Pay the relevant commitment fees of Kshs. 55,000/= for bungalows and Maisonettes, Kshs.55,000/= for Classrooms and Kshs. 300,000/= for blocks of flats, projects and Complete Schools
  • Submit your detailed plans for review, moderation and preparation of Bill of Quantities by Koto Housing Kenya Limited.
  • Receive revised and signed architectural plans and Bill of Quantities.
  • Organise financing for the construction cost of the house/project e.g through savings, or take a mortgage loan from one of our partners.
  • Sign the KOTO Building Contract.
  • Pay the construction cost as per the agreed Priced Bills of Quantities
  • KOTO Housing Kenya Limited builds your dream house as per the construction delivery contract

Other Koto Requirements

Other Koto Requirements
  • Ensure your plot is fenced or there is adequate security on site
  • Ensure utilities e.g water / electricity / sewer are on site
  • Sketch plan showing site and relevant access roads to your site
  • Ensure your land is levelled and is firm.
County Licence Requirements for Approval of Building Plans
  • A current certified copy of the title deed from the ministry of Lands ( 3 Months or Less)
  • Relevant Rates Receipt for current year
  • Copy of previously approved plans (if redeveloping existing building)